Hunter College

Continual project beginning in 2014. Supplied and installed 10 Ton Chillers, Mitsubishi splits, and performed removal and replacements of existing equipment.

Packer Collegiate Institute

Supply and install QTY (2) Mitsubishi model Air Handlers (3 & 2 tons) w/ filter boxes, QTY (1) Mitsubishi model Wall Mounted Air Evaporator, QTY (1) Mitsubishi model Ducted Air Handler, QTY (12) Mitsubishi Backlit Remote Controllers, QTY (5) Mitsubishi model Drain Pan Sensors, QTY (5) Little Giant Condensate Pumps, QTY (2) Mitsubishi model 5-branch(1) […]

Giorgio Armani Offices

Supplied and installed QTY (2) Mammoth air handlers (1) 32,000 cfm & (1) 10,000 cfm, QTY (1) 5 ton United Air packed unit (IT room), QTY (1) 2 ton IEC fan coil unit, QTY (4) exhaust fans, QTY (53) Anemostat VAVs.

St. Hilda’s St. Hugh’s School

Supplied and installed QTY (10) ArctiChill 300 ton chillers, QTY (2) Yula heat exchangers, QTY (29) McQuay fan coil, QTY (24) Renewaire recovery units, QTY (1) Evapco 300 ton cooling tower, QTY (1) Mitsubishi inverter driver, QTY (3) Mitsubishi wall-mounted units, & QTY (1) Mitsubishi condensing unit. Provided complete Building Management System. Project was completed […]

David Zwirner Gallery

Supplied and installed ArctiChill 53 ton Air-cooled Modular Chiller w/ 60″ door enclosure, Sound Attenuator Roof Curbs, QTY (3) Mitsubishi condensing units totaling 18 tons, QTY (47) Mitsubishi air handlers, QTY (2) Trane custom air handlers totaling 18.5 tons, QTY (17) Neptronic modulating humidifiers, QTY (3) Semco energy recovering units, & QTY (6) Heatcraft duct […]

The Dalton School

Supplied and installed QTY (1) 8 ton condensing unit, QTY (7) fan coil units, QTY (1) Renewaire energy recovering unit w/ fan speed controller, QTY (8) Islandaire thru wall type packaged terminal units.

BFAB, LLC

Supplied and installed (1) TRANE Air Cooled Chiller and Economizer, (2) Trane Air Handlers, (1) TRANE Fan Coil Unit, (1) Blower Coil Unit, (18) JAGA FCU’s, (2) NAILOR FCU’s, (2) MULTIAQUA Wall FCU’s, (8) Greenheck Exhaust Fans. Completed install of Building Management System. Produced and installed Air Distribution System and drain pans. Installed piping for […]

DIA Art Gallery

Office and Gallery spaces including Building Management Systems on multiple floors and building locations. Installed (2) TRANE (25 & 30 Ton) Roof Top Units, (4) TRANE Air Handlers and Condensing Units, (12) Mitsubishi Air handlers and (2) Condensers, (14) VAV’s, (4) Duct Heaters), (7) GREENHECK fans, (10) Verano Radiators, (4) BERKO Electric finned-tube heaters, (7) […]

Brooklyn Navy Yard

Installed (3) DAIKIN Roof Top Units, (22) Air Handling Units, (8) Condensing Units, (15) Electric Base Board Heaters, (6) GREENHECK Fans, and accompanying equipment. Oversaw implementation of Building Management System to include BACNET. Fabricated and installed all duct. Field verified all louvre and grille measurements and installed along with motorized dampers, including Fire Smoke Dampers. […]